Process for Requesting Computer/Software Services
to be Housed in the Boyd Data Center
May 6, 2004
The following is the process for requesting computing
hardware, applications and services to be housed in the Boyd
Data Center.
We ask that you fill out the Boyd Data Center Service Request/Evaluation Form
at http://www.eits.uga.edu/ops/bdc/service-request-form.html.
This will give the Boyd Data Center Evaluation/Implementation Committee the information
needed to evaluate your request. This will occur within 7 working days from
receiving your request. The Committee will then document and respond why we can
or cannot support your request.
If the Committee feels that we can support your request, to
house the services in the Data Center,
they will provide a cost estimate with a proposed action plan and time line. This
will occur within 10 working days from the Evaluation Committee's meeting to
accept your request.
Please be aware of the following information:
- That
centralization of services is not always the right solution.
- There
will be standards pertaining to systems, hardware and security required
for any services supported.
- Departmental
system administration must be done remotely and all on-site support must
be contracted through CITP.
- Cost
estimate will be developed by the Committee with an SLA
and installation plan. This will require your approval before the request will
be accepted.