Network Infrastructure Cabling/Equipment
Request Process for The University of Georgia
Purpose:
This procedure is to clarify the Network Infrastructure Cabling/Equipment
Request Process for Data, Voice and Cable TV for the campus community at UGA
for projects under $1,000,000. We want to insure that the Network
Infrastructure is reliable and delivers the services that are needed to support
the UGA Strategic Plan and the Ten Year Master plan. We also want to provide
the end user with the best, most cost-effective infrastructure solution
possible and provide the standards necessary for qualified contractors to
consistently install a quality Network Infrastructure. This document describes
the process and standards that must be followed by anyone wanting to connect to
the UGA Network Infrastructure.
Standards:
It is the responsibility of anyone wanting to attach new or
newly renovated construction to the UGA Campus Infrastructure to insure that all
UGA Network Infrastructure Standards have been met. The UGA Network
Infrastructure Standards have been developed for Data, Voice and Cable TV and
are located at (http://www.uga.edu/netinfo/standards).
Therefore, new or newly renovated network infrastructure that does not comply
with UGA standards will be refused connection to the Campus Network
Infrastructure until it comes into compliance.
Process Documentation:
The University of Georgia
continues to grow at a fast pace. As a
result we have a large number of requests for support on Network Infrastructure
cabling projects. This covers small job requests, new construction, renovations
and upgrades of the current system.
Since staffing is limited and we have a very heavy volume of
requests coming from many customers at UGA, there needs to be a process that
supports UGA customer needs and streamlines the process to insure that we are
using our resources to the best of our abilities.
Cabling
Wiring/Equipment Request:
What is a Cable
Wiring/Equipment Request?
Cable wiring request is any Data, Voice or Cable TV cabling
requiring an add, move or change and any network equipment needed for the
expansion or growth of the Network that is not
being coordinated by the Real Estate Foundation or UGA Architect.
What is not a
Cable Wiring/Equipment Request?
The adding or changing of telephone features, cell phone
request, pager request, cable TV programming questions, telephone/cable
repairs, general trouble tickets/calls or billing questions. (These requests
should be made through the normal help desk request form or channel.)
Customers Process
(Process Map is Attachment A-1)
For the purpose of this process "Customers" are described as
anyone who is requesting infrastructure cabling/equipment support on projects
at UGA that are not working with the University Architects (OUA) or Real Estate
Foundation (UGAREF). The OUA and UGAREF processes are similar but are broken
out since they work on large projects.
When a customer has a need to have additional infrastructure
cabling/equipment support and they are
not working with the OUA and UGAREF, the following process should take
place:
- Remedy will forward a copy of the work order support
request to EITS coordinators (Data/Voice/Cable TV) and to UGA TEC
Services.
- EITS will send an e-mail to the customer and UGA
TEC Services for verifications of the order. (Attachment
C )
- UGA TEC Services will contact the Customer within
2 working days, unless other arrangements have been agreed to, and
coordinate with the Customer to complete any work except for Network
Electronic Equipment and Outside Cable Plant which EITS will coordinate
unless other arrangements are agreed to.
- UGA TEC Services will use e-mail to notify the
customer and EITS (Data/Voice/Cable TV) that work has been completed.
- EITS, if necessary, will meet with customer and
UGA TEC Services to complete a walk-through. If a final walk-through is required
and there are changes needed, a punch list will be given to UGA TEC
Services with a specified time for the work to be completed.
- EITS will require an approval letter from UGA TEC
Services (Attachment G) stating that the
project is complete and certifying that standards have been met prior to
final payment. The as built drawings with a hard copy and electronically
accessible copy of the testing results must be received by the customer
and EITS before final payment is released.
- If UGA Campus community does not
use TEC Services, they can use other providers as long as they have their
systems certified before connecting to the campus backbone. Certification
may be billed at a standard rate of $30.43 per hour.
Construction and
Renovation Project with the UGA Architect (OUA) (Process Map is Attachment A-2)
- OUA starts by developing a written program of
space requirements which provides the basis for preliminary cost
estimation information.
- OUA will provide the Assumption Standard
Information for UGA Architect Projects (Attachment
D) and forward to the Project Director for Venus.
- The Project Director for Venus will provide
estimates for the cost of the project to OUA (Attachment
E).
- If this is a BOR project we would follow the
EITS Approval Process for the BOR Construction Projects.
- OUA will work with the customers to develop plans
for all new construction projects, and Network Infrastructure will be
based on UGA Standards (http://www.uga.edu/netinfo/standards).
- OUA will develop plans to 80% completion and meet
with appropriate personnel for review. EITS will have two weeks to review
the plans at the managing party's location, unless otherwise specified,
and there will be a project manager identified as the one point of contact
for each project.
- OUA will complete the 100% contract plans,
request a final review and approval on the infrastructure from EITS (Attachment F). EITS will review plans,
document any changes and forward a memorandum/approval letter to the
managing parties recapping any changes. The review/approval letter will be
completed within two weeks of the 100% plans being received in the EITS
Project Director's office or within three weeks if required to review the
plans at another location.
- OUA will send a copy of the completed contract
plans to EITS.
- OUA will request proposal/bids from vendors on inside/outside
network infrastructure, except for electronic equipment. EITS will do
proposals/bids for all electronic equipment necessary to activate all
project related infrastructure.
- OUA will review proposals/bids from vendors; will
review with EITS and the General Contractor to select a low voltage BICSI
certified vendor for the project.
- EITS will make periodic inspections according to
the scope of the project. If a final walk-through is required and there
are changes needed, a punch list will be given to the vendor with a
specified time for the work to be completed.
- EITS will require an approval letter from the
vendor (Attachment G) stating that the
project is complete and certifying that standards have been met prior to
final payment from the General Contractors. The as built drawings with a
hard copy and electronically accessible copy of the testing results must
be received by OUA and EITS before final payment is released.
Construction
Project with the University Real Estate Foundation (UGAREF) (Process Map is Attachment A-2)
- UGAREF starts by developing a written program of
space requirements which provides the basis for preliminary cost
estimation information.
- If this is a project over $1,000,000 we would
follow the EITS Approval Process for the BOR Construction Projects.
- UGAREF will work with the customers to develop
plans for all new construction projects and Network Infrastructure will be
based on UGA Standards at http://www.uga.edu/netinfo/standards.
- UGAREF will develop plans to 80% completion and
meet with appropriate personnel for review. EITS will have two weeks to review the
plans at the managing party's location, unless otherwise specified, and
there will be a project manager identified as the one point of contact for
each project.
- UGAREF will complete the 100% contract plans and
request a final review and approval on the infrastructure from EITS (Attachment F). EITS will review plans,
document any changes and forward a memorandum/approval letter to the
managing parties recapping any changes. The review/approval letter will be
completed within two weeks of the 100% plans being received in the EITS
Project Director's office or within three weeks if required to review the
plans at another location.
- UGAREF will send a copy of the completed contract
plans to EITS.
- EITS will meet with the UGAREF Architect at their
request to provide support and review questions/concerns on any project.
- UGAREF will request proposal/bids from vendors on
inside/outside network infrastructure and electronic equipment. EITS will
review all proposals/bids for all electronic equipment necessary to
activate all project related infrastructure before bids are presented to
vendors. EITS will review all proposals/bids within 3 business days of
receiving the completed documentation at their office or will schedule a
proposal/bid review with the UGAREF Project Manager/Architect as schedules
permits.
- UGAREF will review vendor proposals,
select a low voltage BICSI certified vendor and request that EITS attend a
vendor meeting before Network Infrastructure work is started.
- EITS will make periodic inspections according to
the scope of the project. If a final walk-through is required and there
are changes needed, a punch list will be given to the vendor with a
specified time for the work to be completed.
- EITS will require an approval letter from the
vendor (Attachment G) stating that the
project is complete and certifying that standards have been met prior to
final payment from the General Contractors. The as built drawings with a
hard copy and electronically accessible copy of the testing results must
be received by UGAREF and EITS before final payment is released.
Vendors:
- EITS,
UGA Architect and Real Estate Foundation will insure that all vendors
working on Infrastructure are aware of the UGA Network Infrastructure
standards for Data, Voice and Cable TV.
- All network
infrastructure related materials ordered for a
project and not used on that project will be inventoried and controlled
for future projects.
Technology and
Standards:
General
information:
·
Bids should be a Turn Key Project and include
all cost, labor, documentation, testing and material to activate every port
include in the project. The electronics, switches, hubs, routers, etc. are the
only components that will not be included in every project.
·
All projects will have as built drawings. They
should show the layout of the buildings, cable/wiring paths, and all outlet
locations with jack ID's included.
·
All Network Infrastructure cabling projects must
be certified before they can be connected to the Network Infrastructure
backbone.